Got around to cutting the valve seats and surfacing the heads today. Machine work is now done. 4 angles on the seats, (technically 5, but the chamber cutter only left its radius, not the flat, so I’m not counting it), performed just a tad more hand blending after using the chamber cutter. Intake seats are .040” wide, exhaust seats are .060” wide. Both intake and exhaust valve also have a 30 degree back cut.
During surfacing, I only took .004” off each head, they both cleaned up 100% in .003”. (A huge thank you to my wife for not overheating the engine over the past 160,xxx miles).
Next step is to CC the chambers, setup the valve train, final clean, assembly, then attach the heads to the short block.
Intake and exhaust seats just after the first cut, 3 angles, (30, 45 and 60 degrees). The final 2 angles are added with separate cutters.
Ready to be removed from the mill after being surfaced;
Machine work done, awaiting final clean;